TEXAS PROPERTY CODE [Mechanic's Lien Statutes enacted through September 1, 2011] [Does not include any changes arising through subsequent enactments]
CHAPTER 53. MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN
TABLE OF CONTENTS
SUBCHAPTER A. GENERAL PROVISIONS
§ 53.001. Definitions
§ 53.002. More Than One Original Contractor
§ 53.003. Notices"
§ 53.004. reserved for expansion
§ 53.020. reserved for expansion
SUBCHAPTER B PERSONS ENTITLED TO LIEN; SUBJECT PROPERTY
§ 53.021. Persons Entitled to Lien
§ 53.022. Property to Which Lien Extends
§ 53.023. Payment Secured by Lien
§ 53.024. Limitation on
Subcontractor's Lien
§ 53.025. Limitation on Ordinary Retainage Lien
§ 53.026. Sham Contract
§ 53.027. reserved for expansion
§ 53.028. reserved for expansion
SUBCHAPTER C PROCEDURE FOR PERFECTING LIEN
§ 53.051. Necessary Procedures
§ 53.052. Filing of Affidavit
§ 53.053. Accrual of Indebtedness
§ 53.054. Contents of Affidavit
§ 53.055. Notice of Filed Affidavit
§ 53.056. Derivative Claimant: Notice to Owner or Original Contractor
§ 53.057. Derivative Claimant: Notice for Contractual Retainage Claim
§ 53.058. Derivative Claimant: Notice for Specially Fabricated Items
§ 53.059. Repealed by Acts 1997, 75th Leg., ch. 526, s 24, eff. Sept. 1, 1997
§ 53.060. reserved for expansion
§ 53.080. reserved for expansion
SUBCHAPTER D FUNDS WITHHELD BY OWNER FOLLOWING NOTICE
§ 53.081. Authority to Withhold Funds for Benefit of Claimants
§ 53.082. Time for Which Funds are Withheld
§ 53.083. Payment to Claimant on Demand
§ 53.084. Owner's Liability
§ 53.085. Affidavit Required
§ 53.086. reserved for expansion
§ 53.100. reserved for expansion
SUBCHAPTER E REQUIRED RETAINAGE FOR BENEFIT OF LIEN CLAIMANTS
§ 53.101. Required Retainage
§ 53.102. Payment Secured by Retainage
§ 53.103. Lien on Retained Funds
§ 53.104. Preferences
§ 53.105. Owner's Liability for Failure to Retain
§ 53.106. Affidavit of Completion
§ 53.107. Notice Relating to Termination of Work or Abandonment of Performance by Original   Contractor or Owner
§ 53.120. reserved for expansion
SUBCHAPTER F PRIORITIES AND PREFERENCES
§ 53.121. Preference Over Other Creditors
§ 53.122. Equality of Mechanic's Liens
§ 53.123. Priority of Mechanic's Lien Over Other Liens
§ 53.124. Inception of Mechanic's Lien
§ 53.125. reserved for expansion
§ 53.150. reserved for expansion
SUBCHAPTER G RELEASE AND FORECLOSURE; ACTION ON CLAIM
§ 53.151. Enforcement of Remedies Against Money Due Original Contractor or Subcontractor
§ 53.152. Release of Claim or Lien
§ 53.153. Defense of Actions
§ 53.154. Foreclosure
§ 53.155. Transfer of Property Sold
§ 53.156. Costs and Attorney's Fees
§ 53.157. Discharge of Lien
§ 53.158. Period for Bringing Suit to Foreclose Lien
§ 53.159. Obligation to Furnish Information
§ 53.160. Summary Motion to Remove Invalid or Unenforceable Lien
§ 53.161. Bond Requirements After Order to Remove
§ 53.162. Revival of Removed Lien
§ 53.163. reserved for expansion
§ 53.170. reserved for expansion
SUBCHAPTER H BOND TO INDEMNIFY AGAINST LIEN
§ 53.171. Bond
§ 53.172. Bond Requirements
§ 53.173. Notice of Bond
§ 53.174. Recording of Bond and Notice
§ 53.175. Action on Bond
§ 53.176. Repealed by Acts 1989, 71st Leg., ch. 1138, s 39(2), eff. Sept. 1, 1989
§ 53.177. reserved for expansion
§ 53.200. reserved for expansion
SUBCHAPTER I BOND TO PAY LIENS OR CLAIMS
§ 53.201. Bond
§ 53.202. Bond Requirements
§ 53.203. Recording of Bond and Contract
§ 53.204. Reliance on Record
§ 53.205. Enforceable Claims
§ 53.206. Perfection of Claim
§ 53.207. Owner's Notice of Claim to Surety
§ 53.208. Action on Bond
§ 53.209. Repealed by Acts 1989, 71st Leg., ch. 1138, s 39(3), eff. Sept. 1, 1989
§ 53.210. Claims in Excess of Bond Amount
§ 53.211. Attempted Compliance
§ 53.212. reserved for expansion
§ 53.230. reserved for expansion
SUBCHAPTER J LIEN ON MONEY DUE PUBLIC WORKS CONTRACTOR
§ 53.231. Lien
§ 53.232. To Whom Notice Given; Manner
§ 53.233. Contents of Notice
§ 53.234. Time for Notice
§ 53.235. Official to Retain Funds
§ 53.236. Bond for Release of Lien
§ 53.237. Bond Requirements
§ 53.238. Notice of Bond
§ 53.239. Action on Bond
§ 53.240. Repealed by Acts 1989, 71st Leg., ch. 1138, s 39(4), eff. Sept. 1, 1989
SUBCHAPTER K RESIDENTIAL CONSTRUCTION PROJECTS
§ 53.251. Procedures for Residential Construction Projects
§ 53.252. Derivative Claimant: Notice to Owner or Original Contractor
§ 53.253. Derivative Claimant: Notice for Specially Fabricated Items
§ 53.254. Homestead
§ 53.255. Disclosure Statement Required for Residential Construction Contract
§ 53.256. List of Subcontractors and Suppliers
§ 53.257. Provisions Related to Closing of Loan for Construction of Improvements
§ 53.258. Disbursements of Funds
§ 53.259. Final Bills-Paid Affidavit Required
§ 53.260. Conveyance to Contractor Not Required
SUBCHAPTER L Waiver and Release of Lien or Payment Bond Claim
§53.281. Waiver and Release of Lien or Payment Bond Claim
§53.282. Conditions for Waiver, Release, or Impairment of Lien or Payment Bond Claim
§53.283. Unconditional Waiver and Release: Payment Required
§53.284. Forms for Waiver and Release of Lien or Payment Bond Claim
§53.286. Public Policy
§53.287. Certain Agreements Exempt
CHAPTER 53. MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN
SUBCHAPTER A. GENERAL PROVISIONS
§ 53.001. Definitions
In this chapter:
(1) "Contract price" means the cost to the owner for any part of construction or repair performed under an original contract.
(2) "Improvement" includes:
(A) abutting sidewalks and streets and utilities in or on those sidewalks and streets;(B) clearing, grubbing, draining, or fencing of land;
(C) wells, cisterns, tanks, reservoirs, or artificial lakes or pools made for supplying or storing water;
(D) pumps, siphons, and windmills or other machinery or apparatuses used for raising water for stock, domestic use, or irrigation; and
(E) planting orchard trees, grubbing out orchards and replacing trees, and pruning of orchard trees.
(3) "Labor" means labor used in the direct prosecution of the work.
(4) "Material" means all or part of:
(A) the material, machinery, fixtures, or tools incorporated into the work, consumed in the direct prosecution of the work, or ordered and delivered for incorporation or consumption;
(B) rent at a reasonable rate and actual running repairs at a reasonable cost for construction equipment used or reasonably required and delivered for use in the direct prosecution of the work at the site of the construction or repair; or
(C) power, water, fuel, and lubricants consumed or ordered and delivered for consumption in the direct prosecution of the work.
(5) "Mechanic's lien" means the lien provided by this chapter.
(6) "Original contract" means an agreement to which an owner is a party either directly or by implication of law.
(7) "Original contractor" means a person contracting with an owner either directly or through the owner's agent.
(8) "Residence" means a single-family house, duplex, triplex, or quadruplex or a unit in a multiunit structure used for residential purposes that is:
(A) owned by one or more adult persons; and
(B) used or intended to be used as a dwelling by one of the owners.
(9) "Residential construction contract" means a contract between an owner and a contractor in which the contractor agrees to construct or repair the owner's residence, including improvements appurtenant to the residence.
(10) "Residential construction project" means a project for the construction or repair of a new or existing residence, including improvements appurtenant to the residence, as provided by a residential construction contract.
(11) "Retainage" means an amount representing part of a contract payment that is not required to be paid to the claimant within the month following the month in which labor is performed, material is furnished, or specially fabricated material is delivered. The term does not include retainage under Subchapter E.
(12) "Specially fabricated material" means material fabricated for use as a component of the construction or repair so as to be reasonably unsuitable for use elsewhere.
(13) "Subcontractor" means a person who has furnished labor or materials to fulfill an obligation to an original contractor or to a subcontractor to perform all or part of the work required by an original contract.
(14) "Work" means any part of construction or repair performed under an original contract.
(15) "Completion" of an original contract means the actual completion of the work, including any extras or change orders reasonably required or contemplated under the original contract, other than warranty work or replacement or repair of the work performed under the contract.
§ 53.002. More Than One Original Contractor
On any work there may be more than one original contractor for purposes of this chapter.
§ 53.003. Notices
(a) This section applies to notices required by Subchapters B through G and K.
(b) Any notice or other written communication may be delivered in person to the party entitled to the notice or to that party's agent, regardless of the manner prescribed by law.(c) If notice is sent by registered or certified mail, deposit or mailing of the notice in the United States mail in the form required constitutes compliance with the notice requirement. This subsection does not apply if the law requires receipt of the notice by the person to whom it is directed.
(d) If a written notice is received by the person entitled to receive it, the method by which the notice was delivered is immaterial.
§ 53.021. Persons Entitled to Lien
(a) A person has a lien if:
(1) the person labors, specially fabricates material, or furnishes labor or materials for construction or repair in this state of:
(A) a house, building, or improvement;
(B) a levee or embankment to be erected for the reclamation of overflow land along a river or creek; or
(C) a railroad; and
(2) the person labors, specially fabricates the material, or furnishes the labor or materials under or by virtue of a contract with the owner or the owner's agent, trustee, receiver, contractor, or subcontractor.
(b) A person who specially fabricates material has a lien even if the material is not delivered.
(c) An architect, engineer, or surveyor who prepares a plan or plat under or by virtue of a written contract with the owner or the owner's agent, trustee, or receiver in connection with the actual or proposed design, construction, or repair of improvements on real property or the location of the boundaries of real property has a lien on the property.
(d) A person who provides labor, plant material, or other supplies for the installation of landscaping for a house, building, or improvement, including the construction of a retention pond, retaining wall, berm, irrigation system, fountain, or other similar installation, under or by virtue of a written contract with the owner or the owner's agent, contractor, subcontractor, trustee, or receiver has a lien on the property.
(e) A person who performs labor as part of, or who furnishes labor or materials for, the demolition of a structure on real property under or by virtue of a written contract with the owner of the property or the owner's agent, trustee, receiver, contractor, or subcontractor has a lien on the property.
§ 53.022. Property to Which Lien Extends
(a) The lien extends to the house, building, fixtures, or improvements, the land reclaimed from overflow, or the railroad and all of its properties, and to each lot of land necessarily connected or reclaimed.
(b) The lien does not extend to abutting sidewalks, streets, and utilities that are public property.
(c) A lien against land in a city, town, or village extends to each lot on which the house, building, or improvement is situated or on which the labor was performed.
(d) A lien against land not in a city, town, or village extends to not more than 50 acres on which the house, building, or improvement is situated or on which the labor was performed.
§ 53.023. Payment Secured by Lien
The lien secures payment for:
(1) the labor done or material furnished for the construction or repair;
(2) the specially fabricated material, even if the material has not been delivered or incorporated into the construction or repair, less its fair salvage value; or
(3) the preparation of a plan or plat by an architect, engineer, or surveyor in accordance with Section 53.021(c).
§ 53.024. Limitation on Subcontractor's Lien
The amount of a lien claimed by a subcontractor may not exceed:
(1) an amount equal to the proportion of the total subcontract price that the sum of the labor performed, materials furnished, materials specially fabricated, reasonable overhead costs incurred, and proportionate profit margin bears to the total subcontract price; minus
(2) the sum of previous payments received by the claimant on the subcontract.
§ 53.025. Limitation on Ordinary Retainage Lien
A lien for retainage is valid only for the amount specified to be retained in the contract, including any amendments to the contract, between the claimant and the original contractor or between the claimant and a subcontractor.
§ 53.026. Sham Contract
(a) A person who labors, specially fabricates materials, or furnishes labor or materials under a direct contractual relationship with another person is considered to be in direct contractual relationship with the owner and has a lien as an original contractor, if:
(1) the owner contracted with the other person for the construction or repair of a house, building, or improvements and the owner can effectively control that person through ownership of voting stock, interlocking directorships, or otherwise;
(2) the owner contracted with the other person for the construction or repair of a house, building, or improvements and that other person can effectively control the owner through ownership of voting stock, interlocking directorships, or otherwise; or
(3) the owner contracted with the other person for the construction or repair of a house, building, or improvements and the contract was made without good faith intention of the parties that the other person was to perform the contract.
(b) In this section, "owner" does not include a person who has or claims a security interest only.
[Sections 53.027 to 53.050 reserved for expansion]
SUBCHAPTER C
PROCEDURE FOR PERFECTING LIEN
§ 53.051. Necessary Procedures
To perfect the lien, a person must comply with this subchapter.
§ 53.052. Filing of Affidavit
(a) Except as provided by Subsection (b), the person claiming the lien must file an affidavit with the county clerk of the county in which the property is located or into which the railroad extends not later than the 15th day of the fourth calendar month after the day on which the indebtedness accrues.
(b) A person claiming a lien arising from a residential construction project must file an affidavit with the county clerk of the county in which the property is located not later than the 15th day of the third calendar month after the day on which the indebtedness accrues.
(c) The county clerk shall record the affidavit in records kept for that purpose and shall index and cross-index the affidavit in the names of the claimant, the original contractor, and the owner. Failure of the county clerk to properly record or index a filed affidavit does not invalidate
the lien.
§ 53.053. Accrual of Indebtedness
(a) For purposes of Section 53.052, indebtedness accrues on a contract under which a plan or plat is prepared, labor was performed, materials furnished, or specially fabricated materials are to be furnished in accordance with this section.
(b) Indebtedness to an original contractor accrues:
(1) on the last day of the month in which a written declaration by the original contractor or the owner is received by the other party to the original contract stating that the original contract has been terminated; or
(2) on the last day of the month in which the original contract has been completed, finally settled, or abandoned.
(c) Indebtedness to a subcontractor, or to any person not covered by Subsection (b) or (d), who has furnished labor or material to an original contractor or to another subcontractor accrues on the last day of the last month in which the labor was performed or the material furnished.
( d) Indebtedness for specially fabricated material accrues:
(1) on the last day of the last month in which materials were delivered;
(2) on the last day of the last month in which delivery of the last of the material would normally have been required at the job site; or
(3) on the last day of the month of any material breach or termination of the original contract by the owner or contractor or of the subcontract under which the specially fabricated material was furnished.
(e) A claim for retainage accrues on the earliest of the last day of the month in which all work called for by the contract between the owner and the original contractor has been completed, finally settled, terminated, or abandoned.
§ 53.054. Contents of Affidavit
(a) The affidavit must be signed by the person claiming the lien or by another person on the claimant's behalf and must contain substantially:
(1) a sworn statement of the amount of the claim;
(2) the name and last known address of the owner or reputed owner;
(3) a general statement of the kind of work done and materials furnished by the claimant and, for a claimant other than an original contractor, a statement of each month in which the work was done and materials furnished for which payment is requested;
(4) the name and last known address of the person by whom the claimant was employed or to whom the claimant furnished the materials or labor;
(5) the name and last known address of the original contractor;
(6) a description, legally sufficient for identification, of the property sought to be charged with the lien;
(7) the claimant's name, mailing address, and, if different, physical address; and
(8) for a claimant other than an original contractor, a statement identifying the date each notice of the claim was sent to the owner and the method by which the notice was sent.
(b) The claimant may attach to the affidavit a copy of any applicable written agreement or contract and a copy of each notice sent to the owner.
(c) The affidavit is not required to set forth individual items of work done or material furnished or specially fabricated. The affidavit may use any abbreviations or symbols customary in the trade.
§ 53.055. Notice of Filed Affidavit
(a) A person who files an affidavit must send a copy of the affidavit by registered or certified mail to the owner or reputed owner at the owner's last known business or residence address not later than the fifth day after the date the affidavit is filed with the county clerk.
(b) If the person is not an original contractor, the person must also send a copy of the affidavit to the original contractor at the original contractor's last known business or residence address within the same period.
§ 53.056. Derivative Claimant: Notice to Owner or Original Contractor
(a) Except as provided by Subchapter K, a claimant other than an original contractor must give the notice prescribed by this section for the lien to be valid.
(b) If the lien claim arises from a debt incurred by a subcontractor, the claimant must give to the original contractor written notice of the unpaid balance. The claimant must give the notice not later than the 15th day of the second month following each month in which all or part of the claimant's labor was performed or material delivered. The claimant must give the same notice to the owner or reputed owner and the original contractor not later than the 15th day of the third month following each month in which all or part of the claimant's labor was performed or material or specially fabricated material was delivered.
(c) If the lien claim arises from a debt incurred by the original contractor, the claimant must give notice to the owner or reputed owner, with a copy to the original contractor, in accordance with Subsection (b).
(d) To authorize the owner to withhold funds under Subchapter D, the notice to the owner must state that if the claim remains unpaid, the owner may be personally liable and the owner's property may be subjected to a lien unless:
(1) the owner withholds payments from the contractor for payment of the claim;
or
(2) the claim is otherwise paid or settled.
(e) The notice must be sent by registered or certified mail and must be addressed to the owner or reputed owner or the original contractor, as applicable, at his last known business or residence address.
(f) A copy of the statement or billing in the usual and customary form is sufficient as notice under this section.
§ 53.057. Derivative Claimant: Notice for Contractual Retainage Claim
(a) A claimant may give notice under this section instead of or in addition to notice under Section 53.056 or 53.252 if the claimant is to labor, furnish labor or materials, or specially fabricate materials, or has labored, furnished labor or materials, or specially fabricated materials, under an agreement with an original contractor or a subcontractor providing for retainage.
(b) The claimant must give the owner or reputed owner notice of contractual retainage not later than the earlier of:
(1) the 30th day after the date the claimant's agreement providing for retainage is completed, terminated, or abandoned; or
(2) the 30th day after the date the original contract is terminated or abandoned.
(b-1) If an agreement for contractual retainage is with a subcontractor, the claimant must also give the notice of contractual retainage to the original contractor within the period prescribed by Subsection (b).
(c) The notice must generally state the existence of a requirement for retainage and contain:
(1) the name and address of the claimant; and
(2) if the agreement is with a subcontractor, the name and address of the subcontractor.
(d) The notice must be sent to the last known business or residence address of the owner or reputed owner or the original contractor, as applicable.
(e) If a claimant gives notice under this section and Section 53.055 or, if the claim relates to a residential construction project, under this section and Section 53.252, the claimant is not required to give any other notice as to the retainage.
(f) A claimant has a lien on, and the owner is personally liable to the claimant for, the retained funds under Subchapter E if the claimant:
(1) gives notice in accordance with this section and:
(A) complies with Subchapter E; or
(B) files an affidavit claiming a lien not later than the earliest of:
(i) the date required for filing an affidavit under Section 53.052;
|